Northern Nevada Homes, LLC v. GL Construction, Inc.

by
The Supreme Court affirmed the district court’s order awarding attorney fees and costs to Defendant on its counterclaim after the court determined Defendant to be the “prevailing party” following bifurcated trials, in which the parties settled as to damages on Plaintiff’s claims in an amount that exceeded Defendant’s damages judgment on its counterclaim.Specifically, the Court held that the district court did not abuse its discretion by failing to aggregate the settlement recovery and damages award in this case because (1) there is no Nevada statute or court rule that requires the trial court to offset a damages judgment on one party’s counterclaim by the amount recovered by another party in settling its claim to determine which side is the prevailing party; and (2) the most reasonable interpretation of Nev. Rev. Stat. 18.010(2)(a) and 18.020(3) precludes the use of settlement recovery for this purpose. View "Northern Nevada Homes, LLC v. GL Construction, Inc." on Justia Law